HV SWITCHBOARD REPLACEMENT - BHP MINING AREA C (MAC)

Eminence Energy supported a major electrical contractor on a mining project at BHP's Mining Area C (MAC), providing supervision coverage across dayshift and nightshift during a critical 3-week shutdown.

The scope involved:
▪️Removal and replacement of three end-of-life Reyrolle HV switchboards.
▪️Floor strengthening works to support new switchgear.
▪️Commissioning and plant ramp-up.

Thanks to the collaborative effort across all teams, three critical assets are now fully operational, ensuring continued reliability and performance for site operations.

This project demonstrates part of our core offerings at Eminence Energy — delivering specialist services, HV switchboard upgrades, and commissioning support within high-pressure shutdown environments. Our expertise in project execution and collaboration ensures safe, reliable, and efficient outcomes for our clients across Western Australia’s mining and industrial sectors.

Eminence Energy

CONTACT US

4/80 HASLER ROAD

OSBORNE PARK, WA, 6017

EC:16774

ABN: 96 683 419 963

  • LinkedIn
  • Facebook

© 2025 by Eminence Energy. All rights reserved.

bottom of page